The post FAA raises Boeing 737 Max production cap to 42 a month appeared on BitcoinEthereumNews.com. Boeing 737 Max aircraft are assembled at the company’s plant in Renton, Washington, U.S. June 25, 2024. Jennifer Buchanan | Via Reuters Boeing has won regulator approval to ramp up production of its best-selling 737 Max jetliners to 42 a month, a milestone for the manufacturer nearly two years after the Federal Aviation Administration capped its output after a midair near-catastrophe. In January 2024, the FAA restricted Boeing to building the planes at a rate of no more than 38 a month — though it had been below that level at the time — after a door plug from a nearly new 737 Max 9 blew off from an Alaska Airlines flight as it climbed out of Portland, Oregon. Boeing failed to reinstall key bolts on the door plug before it left the factory, a National Transportation Safety Board report found. The 737 Max returned and landed safely, but it put the company back into crisis mode just as leaders were expecting a turnaround year. The FAA said Friday that it would still oversee Boeing’s production. “FAA safety inspectors conducted extensive reviews of Boeing’s production lines to ensure that this small production rate increase will be done safely,” the agency said in a statement. Boeing said it would work with its suppliers to increase production. “We appreciate the work by our team, our suppliers and the FAA to ensure we are prepared to increase production with safety and quality at the forefront,” Boeing said Friday in a statement. Read more CNBC airline news An increase in output is key to the company’s turnaround after years of problems, since airlines and other customers pay for the bulk of an aircraft when they receive it. CEO Kelly Ortberg, named last year to stabilize the top U.S. manufacturer, said last month he expected to soon win FAA approval… The post FAA raises Boeing 737 Max production cap to 42 a month appeared on BitcoinEthereumNews.com. Boeing 737 Max aircraft are assembled at the company’s plant in Renton, Washington, U.S. June 25, 2024. Jennifer Buchanan | Via Reuters Boeing has won regulator approval to ramp up production of its best-selling 737 Max jetliners to 42 a month, a milestone for the manufacturer nearly two years after the Federal Aviation Administration capped its output after a midair near-catastrophe. In January 2024, the FAA restricted Boeing to building the planes at a rate of no more than 38 a month — though it had been below that level at the time — after a door plug from a nearly new 737 Max 9 blew off from an Alaska Airlines flight as it climbed out of Portland, Oregon. Boeing failed to reinstall key bolts on the door plug before it left the factory, a National Transportation Safety Board report found. The 737 Max returned and landed safely, but it put the company back into crisis mode just as leaders were expecting a turnaround year. The FAA said Friday that it would still oversee Boeing’s production. “FAA safety inspectors conducted extensive reviews of Boeing’s production lines to ensure that this small production rate increase will be done safely,” the agency said in a statement. Boeing said it would work with its suppliers to increase production. “We appreciate the work by our team, our suppliers and the FAA to ensure we are prepared to increase production with safety and quality at the forefront,” Boeing said Friday in a statement. Read more CNBC airline news An increase in output is key to the company’s turnaround after years of problems, since airlines and other customers pay for the bulk of an aircraft when they receive it. CEO Kelly Ortberg, named last year to stabilize the top U.S. manufacturer, said last month he expected to soon win FAA approval…

FAA raises Boeing 737 Max production cap to 42 a month

Boeing 737 Max aircraft are assembled at the company’s plant in Renton, Washington, U.S. June 25, 2024.

Jennifer Buchanan | Via Reuters

Boeing has won regulator approval to ramp up production of its best-selling 737 Max jetliners to 42 a month, a milestone for the manufacturer nearly two years after the Federal Aviation Administration capped its output after a midair near-catastrophe.

In January 2024, the FAA restricted Boeing to building the planes at a rate of no more than 38 a month — though it had been below that level at the time — after a door plug from a nearly new 737 Max 9 blew off from an Alaska Airlines flight as it climbed out of Portland, Oregon.

Boeing failed to reinstall key bolts on the door plug before it left the factory, a National Transportation Safety Board report found. The 737 Max returned and landed safely, but it put the company back into crisis mode just as leaders were expecting a turnaround year.

The FAA said Friday that it would still oversee Boeing’s production. “FAA safety inspectors conducted extensive reviews of Boeing’s production lines to ensure that this small production rate increase will be done safely,” the agency said in a statement.

Boeing said it would work with its suppliers to increase production.

“We appreciate the work by our team, our suppliers and the FAA to ensure we are prepared to increase production with safety and quality at the forefront,” Boeing said Friday in a statement.

Read more CNBC airline news

An increase in output is key to the company’s turnaround after years of problems, since airlines and other customers pay for the bulk of an aircraft when they receive it. CEO Kelly Ortberg, named last year to stabilize the top U.S. manufacturer, said last month he expected to soon win FAA approval to raise output to 42, with other increases planned for down the line.

“We’ll go from 42 and then we’ll go up another five, and we’ll go up another five,” Ortberg told a Morgan Stanley investor conference in September. “We’ll get to where that inventory is more balanced with the supply chain, probably around the 47 a month production rate.”

The change shows the FAA’s softening tone and increased confidence in Boeing after years of restrictions. Last month, the agency said it would allow Boeing to again sign off on some of its aircraft itself before they’re handed over to customers, instead of that responsibility falling solely with the FAA.

The Max program was crippled following two crashes of the planes in 2018 and 2019, which killed all 346 people on the two flights. The aircraft was grounded for nearly two years. Covid also hurt production, followed by supply chain problems and, last year, a labor strike at Boeing’s main factories in the Seattle area.

Boeing hasn’t posted an annual profit since 2018. But it has increased output, and its deliveries of new planes are on track to hit the highest rate since that year.

Boeing is scheduled to release quarterly results on Oct. 29.

— CNBC’s Phil LeBeau and Meghan Reeder contributed to this report.

Source: https://www.cnbc.com/2025/10/17/boeing-737-max-production.html

Market Opportunity
Capverse Logo
Capverse Price(CAP)
$0.12822
$0.12822$0.12822
-1.46%
USD
Capverse (CAP) Live Price Chart
Disclaimer: The articles reposted on this site are sourced from public platforms and are provided for informational purposes only. They do not necessarily reflect the views of MEXC. All rights remain with the original authors. If you believe any content infringes on third-party rights, please contact service@support.mexc.com for removal. MEXC makes no guarantees regarding the accuracy, completeness, or timeliness of the content and is not responsible for any actions taken based on the information provided. The content does not constitute financial, legal, or other professional advice, nor should it be considered a recommendation or endorsement by MEXC.

You May Also Like

Ethereum unveils roadmap focusing on scaling, interoperability, and security at Japan Dev Conference

Ethereum unveils roadmap focusing on scaling, interoperability, and security at Japan Dev Conference

The post Ethereum unveils roadmap focusing on scaling, interoperability, and security at Japan Dev Conference appeared on BitcoinEthereumNews.com. Key Takeaways Ethereum’s new roadmap was presented by Vitalik Buterin at the Japan Dev Conference. Short-term priorities include Layer 1 scaling and raising gas limits to enhance transaction throughput. Vitalik Buterin presented Ethereum’s development roadmap at the Japan Dev Conference today, outlining the blockchain platform’s priorities across multiple timeframes. The short-term goals focus on scaling solutions and increasing Layer 1 gas limits to improve transaction capacity. Mid-term objectives target enhanced cross-Layer 2 interoperability and faster network responsiveness to create a more seamless user experience across different scaling solutions. The long-term vision emphasizes building a secure, simple, quantum-resistant, and formally verified minimalist Ethereum network. This approach aims to future-proof the platform against emerging technological threats while maintaining its core functionality. The roadmap presentation comes as Ethereum continues to compete with other blockchain platforms for market share in the smart contract and decentralized application space. Source: https://cryptobriefing.com/ethereum-roadmap-scaling-interoperability-security-japan/
Share
BitcoinEthereumNews2025/09/18 00:25
Husky Inu (HINU) Completes Move To $0.00020688

Husky Inu (HINU) Completes Move To $0.00020688

Husky Inu (HINU) has completed its latest price jump, rising from $0.00020628 to $0.00020688. The price jump is part of the project’s pre-launch phase, which began on April 1, 2025.
Share
Cryptodaily2025/09/18 01:10
SEC dismisses civil action against Gemini with prejudice

SEC dismisses civil action against Gemini with prejudice

The SEC was satisfied with Gemini’s agreement to contribute $40 million toward the full recovery of Gemini Earn investors’ assets lost as a result of the Genesis
Share
Coinstats2026/01/24 06:43